Action scheduled
The entrance to The Mixies from Brook Street
Reported via mobile in the Road Potholes category anonymously at 22:18, Sunday 23 June 2024
Sent to Central Bedfordshire Council less than a minute later. Council ref: 408398.
This pothole has been here for months. More of the cobbles are also becoming loose around it, making the problem area even harder to avoid. There are already 4 cobble stones that have been removed and are on the adjacent path. The hole alongside the cobbles is no longer rideable on a bike
Updates
-
State changed to: Investigating
Updated by Central Bedfordshire Council at 22:18, Sunday 23 June 2024
-
Another resident called regarding this enquiry. Resident advised that the pothole is very deep now and it's very difficult to avoid and needs immediate attention.
State changed to: Open
Posted by Central Bedfordshire Council at 12:51, Friday 9 August 2024
-
Thank you for your Highways report.
An order has now been raised to rectify the identified issue and this will now be added to our programme of works. We are, unfortunately, unable to provide you with a timescale for this work to be completed, however, all repairs are prioritised using an assessment matrix in line with our Network Maintenance Management Plan (NMMP)We will continue to monitor all defects to ensure the safety of our residents as part of the NMMP which can be found online - http://www.centralbedfordshire.gov.uk/ transport/ roads-strategies/ highways-asset-management.aspx
Many thanks,
Central Bedfordshire Council Highways
State changed to: Action scheduled
Posted by Central Bedfordshire Council at 08:58, Wednesday 14 August 2024
Only the original reporter may leave updates. If you made the original report please log in to leave an update.